Installation and disassembly of construction hoist

Release time: 2021-05-29 Visited: 426

Preparation before installation

1 The installation site should have sufficient power supply, and must be equipped with a power box dedicated to the elevator. Each cage should be controlled by a switch. The current of the power supply fuse should be referred to the elevator performance parameter table;

2. The dedicated power box on the construction site should be directly introduced from the transformer room on the construction site, and the distance should not exceed 25m. Generally, one cable is used, or each cage can be connected by one cable. The cable section specification is larger than that of the main cable of the cage. One size bigger. If the distance exceeds 25 meters, the cross-sectional area of the cable should be appropriately increased;

3. Appropriate lifting equipment and installation tools should be available

4. There should be roads and sites for transporting and stacking elevator parts;

5. The user should make the basis as required

6. Determine the connection plan between the attached wall frame and the building, and prepare embedded parts or fixed parts as needed

7. According to user needs, bring your own platform accessories, such as bridge boards, safety railings, platform landing doors, etc.

8. According to relevant regulations and requirements, set up a grounding device to ensure that the grounding resistance is not greater than 4Ω;

9. According to relevant regulations and requirements, the maximum deviation of the site power supply voltage is ±5%, and the power supply is not less than the total power of the motor

10. If the construction site is powered by a generator, it must be equipped with reactive power compensation equipment to ensure power quality

11. The construction site should be equipped with a suitable leakage protection switch.

Parts that need to be provided by the user

1. The lift foundation made according to the requirements, and some 2~12mm thick steel gaskets, used to pad into the chassis and adjust the verticality of the rail frame;

2. Dedicated power box and connecting cable equipped as required;

3. A cable with a suitable specification is used to connect the dedicated power box and the power box of the elevator. The length is generally not more than 25 meters, and the shorter is better.

4. Select the connection scheme of the attached wall frame, prepare the connecting bolts and embedded parts

5. In addition to the special tools provided with the machine, the user needs to prepare a set of installation tools.

Installation safety requirements

1. The installation site should be cleaned up and enclosed with sign poles, etc., and non-workers are forbidden to enter

2. Prevent objects from falling above the installation site, and safety nets should be added when necessary

3. During the installation process, the installation must be carried out by a professionally qualified installer, and at the same time, a dedicated person shall be responsible for the unified command

4. When the lift is running, the head and hands of the personnel must not be exposed outside the safety fence of the cage, let alone outside the driver's cab

5. Don't forget to tighten the link bolts of the standard section and the wall bracket

6. If someone is working on the rail frame, attached wall frame or under the cage, never start the lift. When the cage is raised, it is strictly forbidden to enter the outer cage.

7. All parts on the hanging cage must be placed stably, and the safety fence must not be exposed

8. When using booms for installation, overloading is not allowed. The booms are only used to install or disassemble parts of the elevator, and not for other purposes.

9. Do not move the cage when there are hanging objects on the boom

10. Installation personnel should follow the safety requirements for aerial work, including wearing helmets, safety belts, and non-slip shoes. Do not wear loose clothes and wear work clothes to avoid being caught in moving parts and causing safety accidents.

11. When operating the elevator during installation, the operating box must be brought to the top of the hanging cage, and operation in the hanging cage is not allowed

12. Before starting the hoisting cage, a comprehensive inspection should be carried out to eliminate all hidden dangers of insecurity.

13. During installation and operation, it must be loaded according to the rated load of the elevator, and overload operation is not allowed

14. Installation operations cannot be carried out during thunderstorms, snowy days, or severe weather with wind speeds exceeding 13 m/s

15. When the elevator is running, firstly ensure that the grounding device is connected to the metal structure of the elevator, and the grounding resistance is not greater than 4Ω

16. The numbers of the transmission trolley and the cage must be the same

17. All parts must use the original parts provided by our company, otherwise there will be safety hazards

18. Without the permission of the company, the electrical wiring of the lift shall not be changed

19. Installation is strictly prohibited at night or after drinking

20. The verticality of the guide rail frame must be checked as required for each installation of the attached wall

21. Lubricate as required after installation

免费线上看黄网站入口 | 大鸡巴网站在线免费观看 | 成人小黄书免费网站入口 | 人人看人人澡人人做 | 国产精品毛片一区二区三区, | 97色情一区二区三区 | 成人一区二区在线视频播放免费 | 无码精品少妇一区二区三区久久 | 无码人妻精品一区二区99 | 精品无码红桃二区三区 | 免费的黄色视频网站下载在线 | 日韩一级黄色录像视频 | 天天干天天干天天插天天爽 | 狼人午夜精品AV无码 | 少妇在线视频看A片 | 国产无码在线观看网站 | 亚欧洲精品在线视频 | 538prom精品视频任你爽 | 国產精品久久久久久久 | 精产品99永久免费网页版 | 无套内射无矿码免费看黄 | 亚洲精品毛A久久久天爽 | 久久国产视频限制免费 | 91麻豆产精品久久久久久 | 国产成人AV一区二区三区 | 一级少妇精品内射自慰久久久久久久密乳 | 538prom精品视频任你爽 | 国产裸体美女无遮挡永久免费观看 | 国产精品视频一区二区三区, | 免费无码一区二区 | 狼人色情乱婬一区二区 | 日韩AV电影在线免费观看 | 国产最大最粗无套内谢 | 91肥熟国产老肥熟女hd | 农村偷拍少妇精品一区 | 国产精品久久国产愉拍 | 国产睡熟迷奷系列精品 | 国产伦精品一区二区三区妓女原神 | 亚洲人成色777777精品音频 | 欧洲无码精品a区无人码 | 国产与黑人一级A片免费 |